Bayliss Boatworks new construction updates

by Bayliss Boatworks 3 May 12:40 PDT
 
We are excited to debut the name of the latest 75 build at Bayliss Boatworks: Big Deal. She will be be welcomed into a well established fishing program, and after delivery will kick off her fishing expeditions along the East Coast and will eventually make the journey to Cabo and Costa Rica as well. 
Last month on Big Deal, our exterior carpentry team glassed the bow deck, and worked on installing the toerail and cockpit AC. Our interior carpentry team has been busy putting mockups in place in the master stateroom. Next on the agenda, crews will install her structural cockpit decking and then the mezzanine buildout will begin.
CLICK TO READ MORE ABOUT BIG DEAL
 
Sequentis hit the water for the first-time last month! Earlier in April, our team piled on for her maiden sea trial. Testing and proving was a success, and she has moved back into the make ready bay to receive a few finishing touches on the exterior. The bridge table and helm chair were both installed, while installation of cabinetry below deck remains ongoing. Josh Everett will be completing her transom artwork and we are closing in on the delivery date!
CLICK TO READ MORE ABOUT SEQUENTIS
 
Max Bet saw many improvements last month. Our exterior carpentry team has been busy in the cockpit, installing the teak bullnose in the mezzanine, cockpit decking, and teak coverboards. Awlfair has been applied to the bridge flooring up in the flybridge, and in the interior, the dayhead cabinetry is now installed. Max Bet will be making moves soon and will head over to our paint facility in the next few weeks for topcoat. 
CLICK TO READ MORE ABOUT MAX BET
 
The crews working on Bayliss 64 had a productive month. With the forward fuel tank surround buildout complete, our mechanical team successfully installed the forward fuel tank. Meanwhile, our paint department continues sanding and priming the salon deck, and they recently finished painting the engine room. We are looking forward to Bayliss 64s engine installs scheduled for later this month! 
CLICK TO READ MORE ABOUT BAYLISS 64'
 
 
 
Website
Website
Facebook
Facebook
Instagram
Instagram
Copyright © 2024 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com 

Related Articles

Bayliss 67': Overtime
Delivered in November 2022 and is a product of 64,141 man hours Bayliss built Overtime as the weapon of choice for an assortment of Cabo San Lucas blue water fisheries. Its elaborate livewell system supports transom and on-deck livewells, as well as tuna tubes. Posted on 2 Dec 2022
Designing the Bayliss walkaround
Once someone becomes a Bayliss owner, they become part of a family Sequentis will be the third Bayliss boat for its owner and crew, so when this family member asked for a special, purpose-driven build, Bayliss Boatworks didn't hesitate to take on the challenge. Posted on 2 Aug 2022
Bayliss 75' Wave Paver construction update
Looking back with pride to just over two years ago when her owners approached us Now that our work on the project is finished, we look back with pride to just over two years ago when her owners approached us to discuss their second build. Posted on 3 Jun 2022
Bayliss Boatworks delivers Old Reliable 72'
Nick Smith is the proud owner of the custom sport fishing yacht Bayliss Boatworks is proud to announce the delivery of Old Reliable, a 72' custom sport fishing yacht. Her christening took place on August 6th, in a gathering with friends and family. Posted on 2 Sep 2021
Bayliss Boatworks new construction updates
Old Reliable (Hull 5) paid a visit to Old Reliable (Hull 25) to see how things were going Old Reliable (Hull 5) paid a visit to Old Reliable (Hull 25), to see how things were going in the final stages of her build. With a few successful fishing trips in the books, she is almost ready for christening on August 6th. Posted on 3 Aug 2021
Bayliss 67' Overtime construction update
The right-side up after her recent flip Before the flip, the hull took shape having the sheer line cut and guards installed. The hull also saw the installation of her spray rails, lower guards, lifting strakes and engine intake vents. Posted on 8 Mar 2021
Bayliss 75' construction update
There have been major developments over the past month With her forward sole installation complete, the exterior carpentry crew installed the lower level interior walls showcasing the four stateroom and three head layout. Posted on 6 Mar 2021
Bayliss 72' Old Reliable construction update
Teak decking and coaming boards installed in the cockpit This past month, more details were checked off on the interior and exterior of Old Reliable (Bayliss 72'). Teak decking and coaming boards were installed in the cockpit while mezzanine lids were glassed before receiving their teak decking. Posted on 3 Mar 2021
Bayliss 67' Overtime construction update
The planking process has been completed After receiving three layers of cold-molded okoume plywood on the bottom and two layers on the hull sides, the planking process for Overtime (Bayliss 67') has officially been completed with the placement of her "whiskey plank". Posted on 10 Feb 2021
Bayliss 75' construction update
The interior is progressing quickly Our greatest note was the installation of her 1,150 gallon forward fuel tank by our mechanical crew. Once in place, the paint crew was able to complete fairing, painting and top coat inside the machine tunnel - forward sole installation is next! Posted on 6 Feb 2021