Construction updates: Tarheel Bayliss 62'

by Bayliss Boatworks 3 Jun 09:13 PDT
Tarheel Bayliss 62' © Bayliss Boatworks

After undergoing final clear coats and receiving her Palm Beach Towers hard-top in mid-May, Tarheel (Bayliss 62') emerged from the paint bay looking like a finished boat.

Tarheel also received her transom paint last month, courtesy of Everett Nautical. Our paint crew will focus on applying her waterline and bottom paint over the next couple of weeks.

In Tarheel's interior, the teak salon valences have been installed, the faux-teak salon door is on its tracks, and teak shower doors have been hung in both heads. Our interior carpentry crew is now turning their focus to the installation of the custom TV lift in the salon, granite countertops in the galley, and her teak companionway stairs.

Over the course of the next couple of weeks, Custom Marine Electronics will complete all electronic installations within Tarheel's flybridge console. Our mechanical department has set the bow thruster, salon air handlers and installed the sea chest.

She's nearly ready for her sea trial in early June!

Read more at baylissboatworks.com/boats/gb3

Related Articles

Blue View - Bayliss 78' construction update
Blue View's cockpit bulkhead will soon receive the final coat of clear coat With her tower and hard top installed, Blue View has been nestled in our "make-ready" bay as our crews work on finalizing her exterior paint and installing her interior cabinetry. Posted on 6 Nov
Tarheel, the Bayliss 62' christened
THe first opportunity for Bayliss Boatworksoto create a boat to their very own specifications Bayliss Boatworks was built around our time spent fishing in the ocean. Years of offshore fishing pushed us into boat building, then boat building pushed us into fishing more exotic locations all over the world. Posted on 4 Aug
Construction updates - Tarheel Bayliss 62'
Late June was an exciting time at the shop Our very own 62-foot build is getting close to her christening date! Late June was an exciting time at the shop. Department supervisors gathered in the cockpit on Tarheel (Bayliss 62') as we took her out for the first sea trial. Posted on 4 Jul
Blank Check (Bayliss 75') delivered
Powered with MTU 16V2000 M9L engines, each with 2,600 horsepower The 75' Blank Check was christened and delivered to her owners in early April. A product of over 68,000 man-hours and nearly 28 months of labor, she will be spending much of her time at southern latitudes. Posted on 11 May
Construction updates: Bayliss 75'
It's christening month! While the exterior appearance of this build was finalized in March with the addition of her buggy top, we are seeing changes on the interior daily. Posted on 6 Apr
New construction updates - Bayliss 75'
One of the biggest benchmarks checked off in early February- her first sea trial The month of February made things real for Bayliss 75' as this build nears completion. One of the biggest benchmarks was checked off in early February- her first sea trial. Posted on 3 Mar
GameChanger - GameBoat 62'
GameChanger's build crew is now working towards the installation of the teak deck It's all about teak this month! GameChanger's build crew is now working towards the installation of the teak deck, coverboards, and coaming. As for faux teak, GameChanger has plenty. Posted on 3 Jul 2018
Construction update: GameChanger - GameBoat 62'
GameChanger is a bit different from first GameBoat, the 60' Mama C The GameChanger features our most customizable interior option that seeks to meet our owners' unique fishing needs. GameChanger has a three-stateroom/two-head layout, complete with a custom tackle room. Posted on 6 Jun 2018
GameChanger - GameBoat 62' construction update
GameBoat crew is sighting the half round and window line We are in the midst of both upper and lower level cabinetry fabrication on GameChanger - from floors to cabinets to nightstands. Next on the list is installation of head floors, and various cabinetry in the Master stateroom. Posted on 6 May 2018
Bayliss 75' construction updates
Lower level cabinetry buildout has quickly progressed Our crew will continue to finish out the Master with continued buildout on the headboard and valence. The flooring in both the VIP and Crew staterooms have been installed, and the VIP cabinetry is in the process of being fabricated. Posted on 5 May 2018